Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Panel
panelIconIdatlassian-info
panelIcon:info:
bgColor#ABF5D1

If installing in Canada, this portion of the install requires full shutdown of the main panel.

🪛 Energy Monitor and CT Install

  1. Locate the electrical panels

  2. Safely remove the exterior cover, following established safety protocols.

  3. Install current transformers on each circuit to be monitored

  4. Plug each current transformer into the energy monitor module, labeling each in the mobile app

  5. Install power cord for energy monitor

    (info) Black to

    power

    Power

    remaining

    (info) Remaining to

    neutral

    Neutral

  6. Verify power light is lite on energy monitor.

  7. Record circuit used to power energy monitor in mobile app and label on panel schedule

  8. Click on the Epod showing in the install app.

image-20240425-174507.png

image-20240425-173942.png

(info) Ensure that the correct panel is programmed in app: WYE or Delta (208-480) or single phase.

image-20240425-174733.png

image-20240425-175225.png

image-20240425-200930.png

  1. Secure all wires in clean and orderly fashion

Panel
panelIconIdatlassian-info
panelIcon:info:
bgColor#ABF5D1

Install the proper CT based on the circuit voltage

Slot “0” is only used for monitoring mains 150 single CT

Filter by label (Content by label)
showLabelsfalse
max5
spacescom.atlassian.confluence.content.render.xhtml.model.resource.identifiers.SpaceResourceIdentifier@11b60
sortmodified
showSpacefalse
reversetrue
typepage
labelskb-how-to-article
cqllabel = "kb-how-to-article" and type = "page" and space = "IKB"